Project Duration
Stipulated Date of Commencement
September 25 2021
Actual Date of Completion
September 28 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 561,600.00
Awarded for
₹ 561,600.00
Final Cost of Project
₹ 561600
Project highlights
Supply and Installation of Oxygen Jumbo cylinders for gas manifold
Contractors
M/s. Scoop Industries Pvt. Ltd.
Consultants
M/s. Structwel Designers & Consultants Pvt. Ltd.