Project Duration
Stipulated Date of Commencement
December 12 2011
Stipulated Date of Completion /
Likely Date of Completion April 11 2012
Likely Date of Completion April 11 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,528,636.00
Awarded for
₹ 5,976,204.30
Contractors
M/s. Ask Developers
Consultants
M/s. Datta Kare Associates
Sub Works
This project involved 1 sub works. The details of the same available below
1
Supply, Installation, Testing & Commissioning of Mortuary Cabinet.
100% completed
Project Duration
Stipulated Date of Commencement
December 01 2011
Stipulated Date of Completion /
Likely Date of Completion March 31 2012
Likely Date of Completion March 31 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,058,320.00
Awarded for
₹ 2,406,250.00
Contractors
M/s. Megastar Engineering
Consultants
M/s. Datta Kare Associates
See Similar Projects
External Electrical works
View Project
Supply, Testing and Commissioning of OT Table with Accessories
View Project
Rear Side parking and Biomedical Waste Building
View Project





