Project Duration
Stipulated Date of Commencement
April 22 2016
Actual Date of Completion
May 27 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1.09 Crores
Awarded for
₹ 1.42 crores
Contractors
M/s. R. S. Lawande, M/s. R. S. Lawande
Consultants
M/s. Creative Abode, M/s. Creative Abode