Project Duration
Stipulated Date of Commencement
August 02 2004
Stipulated Date of Completion /
Likely Date of Completion April 28 2005
Likely Date of Completion April 28 2005
Status
100%
Completed
Cost (₹)
Estimated at
₹ 28,100,000.00
Awarded for
₹ 26,864,995.00
Project highlights
To provide hall for social gathering like wedding, community gatherings/functions, exhibitions, etc, with adequate parking space,. The hall is having capacity of around 1200 people and is attached with green rooms and toilet and other amenities like lawn area, with open stage and buffet/ recreational area.

Contractors
M/s. Premier Builders (Goa) Pvt. LTd

Consultants
M/s. Rahul Deshpande & Associates
Sub Works
This project involved 7 sub works. The details of the same available below
1
Landscaping work.
100% completed
Project Duration
Stipulated Date of Commencement
November 03 2005
Stipulated Date of Completion /
Likely Date of Completion December 17 2005
Likely Date of Completion December 17 2005
Status
100%
Completed
Cost (₹)
Estimated at
₹ 325,000.00
Awarded for
₹ 331,000.00

Contractors
M/s. Hariyalee Nursery

Consultants
M/s. Rahul Deshpande & Associates
2
Signages work
100% completed
Project Duration
Stipulated Date of Commencement
January 03 2006
Stipulated Date of Completion /
Likely Date of Completion February 02 2006
Likely Date of Completion February 02 2006
Status
100%
Completed
Cost (₹)
Estimated at
₹ 64,000.00
Awarded for
₹ 65,000.00

Contractors
M/s. Home Deco

Consultants
M/s. Rahul Deshpande & Associates
3
Providing facilities such as acoustics, sound system and DG sets
100% completed
Status
100%
Completed
Project highlights
Providing facilities such as acoustics, sound system and DG sets

Contractors

Consultants
4
Acoustic work.
100% completed
Project Duration
Stipulated Date of Commencement
March 26 2007
Stipulated Date of Completion /
Likely Date of Completion July 25 2007
Likely Date of Completion July 25 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 14,608,159.00
Awarded for
₹ 14,092,186.88

Contractors
M/s. Idea Incorporation

Consultants
M/s. Effective Architectural Services
5
Sound System.
100% completed
Project Duration
Stipulated Date of Commencement
March 26 2007
Stipulated Date of Completion /
Likely Date of Completion July 25 2007
Likely Date of Completion July 25 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,534,853.00
Awarded for
₹ 2,484,551.20

Contractors
M/s. A Square Techno Solution

Consultants
M/s. Effective Architectural Services
6
Air conditioning
100% completed
Project Duration
Stipulated Date of Commencement
March 26 2007
Stipulated Date of Completion /
Likely Date of Completion July 25 2007
Likely Date of Completion July 25 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 20,341,079.00
Awarded for
₹ 17,638,454.00

Contractors
M/s. Vigneshwar Air Conditioning Pvt. Ltd.

Consultants
M/s. Effective Architectural Services
7
Electrical work
100% completed
Project Duration
Stipulated Date of Commencement
March 26 2007
Stipulated Date of Completion /
Likely Date of Completion July 25 2007
Likely Date of Completion July 25 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 8,420,363.00
Awarded for
₹ 8,520,325.00

Contractors
M/s. Lit Homes

Consultants
M/s. Effective Architectural Services

See Similar Projects

Rejuvenation of cluster of lanes of Altinho Steps Phase I
View Project
Acoustics & Miscellaneous work.
View Project
Testing & Commissioning of the fire Fighting, Fire Alarm and PA System
View Project