Project Duration
Stipulated Date of Commencement
August 20 2023
Stipulated Date of Completion /
Likely Date of Completion November 19 2024
Likely Date of Completion November 19 2024
Status
12%
Completed
Cost (₹)
Estimated at
₹ 27,273,704.00
Awarded for
₹ 26,715,496.91
Project highlights
It includes Panchayat office, conference room 3 Nos. shops, ATM, electricity room, post office, multipurpose hall having capacity of 400 people, security cabin toilets etc.
Contractors
M/s. Sirajuddin Beig
Consultants
M/S. Gurudutt Sanzgiri