Project Duration
Stipulated Date of Commencement
August 20 2023
Stipulated Date of Completion /
Likely Date of Completion November 19 2024
Likely Date of Completion November 19 2024
Status
12%
Completed
Cost (₹)
Estimated at
₹ 27,273,704.00
Awarded for
₹ 26,715,496.91
Project highlights
It includes Panchayat office, conference room 3 Nos. shops, ATM, electricity room, post office, multipurpose hall having capacity of 400 people, security cabin toilets etc.
Contractors
M/s. Sirajuddin Beig
Consultants
M/S. Gurudutt Sanzgiri
See Similar Projects
Construction of Wholesale Fish Market at Margao – Phase II
View Project
Construction of New District & Session Court Complex at Merces,Tiswadi,Goa – Interior & Furniture Works.
View Project
Upgradation of Infrastructure in Rural Areas Under Deendayal Panchayat Raj Infrastructure Development (Golden Jubilee) Scheme, 2013 – Renovation of Panchayat Farm and Construction of New Tourist Cottages at V. P. Bhironda
View Project





