Project Duration
Stipulated Date of Commencement
July 22 2023
Stipulated Date of Completion /
Likely Date of Completion July 21 2024
Likely Date of Completion July 21 2024
Status
97%
Completed
Cost (₹)
Estimated at
₹ 351,669,705.00
Awarded for
₹ 325,337,450.83
Project highlights
Interior & Furniture Works for the court building
Contractors
M/s. Godrej and Boyce Mfg. Co. Ltd.
Consultants
M/s. Shrikhande Consultants Ltd.