Project Duration
Stipulated Date of Commencement
November 24 2023
Stipulated Date of Completion /
Likely Date of Completion February 23 2025
Likely Date of Completion February 23 2025
Status
15%
Completed
Cost (₹)
Estimated at
₹ 25,025,749.00
Awarded for
₹ 25,260,845.05
Project highlights
Stilt ground and 1st floor.
Multipurpose hall, shops, panchayat office and gym.
Contractors
M/s. V.Construct
Consultants
M/s. Banaji & Associates