Project Duration
Stipulated Date of Commencement
April 30 2016
Stipulated Date of Completion /
Likely Date of Completion July 29 2017
Likely Date of Completion July 29 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,312,759.00
Awarded for
₹ 14,422,515.20
Project highlights
The building is G+2 structure having Shops – 3 nos, post office, library, Self help group room along with toilets on ground floor, Panchayat office, Gym & toilets on first floor and hall along with dining and toilet facility on second floor.
Contractors
M/s. H. Candolkar & Sons
Consultants
M/s. Bhaskar Wagle & Associates
See Similar Projects
Construction of Panchayat Building at Mauxi in Sattari Taluka.
View Project
Upgradation of Infrastructure in the rural areas under Deendayal Panchayat Raj Infrastructure Development (Golden Jubilee) Scheme , 2013 – Renovation of Panchayat Ghar at V.P Parcem.
View Project
Construction of Multipurpose Hall and Office Building for V.P.Salvador Do Mundo – Additional works.
View Project