Project Duration
Stipulated Date of Commencement July 03 2015
Actual Date of Completion December 20 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 27,759,455.25
Awarded for ₹ 36,700,220.20
Final Cost of Project ₹ 45,780,886.00

Project highlights

Construction of new building for Panchayat Ghar

 
Contractors
M/s. Trivikram Constructions
Consultants
M/s. Oracle Structural Consultants
 