Project Duration
Stipulated Date of Commencement
December 10 2016
Stipulated Date of Completion /
Likely Date of Completion March 09 2018
Likely Date of Completion March 09 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,025,353.00
Awarded for
₹ 14,267,793.55
Project highlights
Lower Ground Floor –
1) It accommodates 6 shops.
2.) 3 shops with area 14.28 sq. m. each and 3 shops with area 25.03 sq. m. each.
Upper Ground Floor –
3) Bank.
4) Post Office
5)Ladies and Gents Toilet.
First Floor –
6)Office of the Village Panchayat.
7) Public Library.
Second Floor –
8) Multipurpose Hall to cater to 180 people, with area of 151.85 Sq.m. with Green Rooms.
9) Dining Hall.
10) Ladies and Gents Toilet.
Contractors
M/s. Mahabaleshwar (M. Naik & Co)
Consultants
M/s. Nilesh Salkar Associates were terminated on 3rd November 2017. Presently, In – House Consultancy. Also, M/s. FP Project Management has provided services during completion stage.
See Similar Projects
Landscaping work in the state of Goa
View Project
Upgradation of Infrastructure in the Rural Areas under Deen Dayal Panchayat Raj Infrastructure Development(Golden Jubilee) Scheme 2013 – Reconstruction of Panchayat Ghar at V.P. Siolim-Sodiem, Siolim, Bardez-Goa
View Project
Lift work.
View Project