Project Duration
Stipulated Date of Commencement
December 10 2016
Stipulated Date of Completion /
Likely Date of Completion March 09 2018
Likely Date of Completion March 09 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,025,353.00
Awarded for
₹ 14,267,793.55
Project highlights
Lower Ground Floor –
1) It accommodates 6 shops.
2.) 3 shops with area 14.28 sq. m. each and 3 shops with area 25.03 sq. m. each.
Upper Ground Floor –
3) Bank.
4) Post Office
5)Ladies and Gents Toilet.
First Floor –
6)Office of the Village Panchayat.
7) Public Library.
Second Floor –
8) Multipurpose Hall to cater to 180 people, with area of 151.85 Sq.m. with Green Rooms.
9) Dining Hall.
10) Ladies and Gents Toilet.
Contractors
M/s. Mahabaleshwar (M. Naik & Co)
Consultants
M/s. Nilesh Salkar Associates were terminated on 3rd November 2017. Presently, In – House Consultancy. Also, M/s. FP Project Management has provided services during completion stage.
See Similar Projects
Audio video
View Project
Upgradation & Restoration of Kala Academy, Panaji, Goa – Civil work
View Project
Construction of Panchayat Ghar and Market Complex at Village Panchayat Neura in St. Andre Constituency.
View Project