Project Duration
Stipulated Date of Commencement
July 23 2019
Stipulated Date of Completion /
Likely Date of Completion November 01 2019
Likely Date of Completion November 01 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 800,000.00
Awarded for
₹ 800,000.00
Project highlights
Project consits of supply, Installation in specified location, Testing and Commissioning of Advanced Non Invasive Ventilator with Humidifier including Compressor for extension of ward 125 for cardiology department
Contractors
M/s. Rescare Medysis I PVT. Ltd.
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
See Similar Projects
Upgradation and extension of existing Cottage Hospital at Chicalim, Goa SH: Demolition of existing structures
View Project
Renovation/ Maintenance of Hospitals, CHCs, PHCs, RMDs, under Directorate of Health Services in North, Goa – SH : Repair of two nos. of 60 KVA UPS installed at Sub District Hospital, Po+C523nda, Goa.
View Project
Minor maintenance/Renovation works at Hospitals,Health Centres and Institutions under Directorate of Health Services in the State of Goa.
View Project