Project Duration
Stipulated Date of Commencement July 23 2019
Stipulated Date of Completion /
Likely Date of Completion
November 01 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 800,000.00
Awarded for ₹ 800,000.00

Project highlights

Project consits of supply, Installation in specified location, Testing and Commissioning of Advanced Non Invasive Ventilator with Humidifier including Compressor for extension of ward 125 for cardiology department

 
Gallery Image
Contractors
M/s. Rescare Medysis I PVT. Ltd.
Gallery Image
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
 
Similar Projects

See Similar Projects

Similar Project

Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in North Goa – S.H. – Maintenance Contract for ten numbers of UPS installed at Sub District Hospital, Ponda for three years

View Project
Similar Project

Remodelling of existing Sewage Treatment Plant for GMC, Bambolim, Goa (C-Tech).

View Project
Similar Project

Steel Operation Theatre

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.