Project Duration
Stipulated Date of Commencement
July 23 2019
Stipulated Date of Completion /
Likely Date of Completion November 01 2019
Likely Date of Completion November 01 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 800,000.00
Awarded for
₹ 800,000.00
Project highlights
Project consits of supply, Installation in specified location, Testing and Commissioning of Advanced Non Invasive Ventilator with Humidifier including Compressor for extension of ward 125 for cardiology department
Contractors
M/s. Rescare Medysis I PVT. Ltd.
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD
See Similar Projects
Supply, installation, testing and commissioning of 2 nos. of 30 KVA UPS
View Project
Upgradation and Extension of Existing Cottage Hospital at Chicalim, Goa – Supply and Installation of Oxygen Jumbo cylinders for gas manifold.
View Project
Renovation/Maintenance of Hospitals, CHC’s, PHC’s, RMD’s under Directorate of Health Services in North Goa – S.H. Replacement of phase barrier sheets in HT panel of Megawin make and one time servicing of 33 KV HT outdoor breaker installed at Sub District Hospital, Ponda – Goa
View Project