Project Duration
Stipulated Date of Commencement September 29 2014
Actual Date of Completion November 21 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 23,472,531.00
Awarded for ₹ 29,708,266.00
Final Cost of Project ₹ 28,953,528.00

Project highlights

Repairs to old dilapated building adjacent to Se Cathedral Church for accomodating the pilgrims attending the Exposition of relics of St. Francis Xavier

 
Contractors
M/s H Candolkar & Sons
Consultants
M/s Creative Abode
 