Project Duration
Stipulated Date of Commencement
June 10 2011
Stipulated Date of Completion /
Likely Date of Completion September 09 2011
Likely Date of Completion September 09 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,480,506.00
Awarded for
₹ 2,884,300.00
Project highlights
Sewage and effluent treatment facility
Contractors
M/s. Sainath Enviro-Tech
Consultants
M/s Effective Architectural Services
Sub Works
This project involved 1 sub works. The details of the same available below
1
Supply, Installation, Testing and Commissioning of 100KLD Sewage Treatment Plant and allied Civil works.
85% completed
Project Duration
Stipulated Date of Commencement
May 31 2023
Stipulated Date of Completion /
Likely Date of Completion July 31 2024
Likely Date of Completion July 31 2024
Status
85%
Completed
Cost (₹)
Estimated at
₹ 27,073,347.00
Awarded for
₹ 23,436,764.00
Project highlights
Providing 100 KLD STP for Hospital Premises along with allied Civil works.
Contractors
M/s. Concept Creator
Consultants
M/s. Saolapurkar and Associates
See Similar Projects
Construction of 450 bedded Ward Block at GMC Complex, Bambolim, Goa. Civil, Plumbing, Electrical and Fire Fighting work.
View Project
Major maintenance works at Goa Medical College and Hospital at Bambolim, Goa – SH – Maintenance of landscaping works.
View Project
Maintenance contract for 8 Nos. of elevators installed at North Goa District Hospital Mapusa for 3 years
View Project