Project Duration
Stipulated Date of Commencement September 22 2017
Actual Date of Completion September 21 2020
Status
100%
Completed
Cost (₹)
Estimated at ₹ 5,714,108.00
Awarded for ₹ 6,196,686.00
Final Cost of Project ₹ 4,642,942.00

Project highlights

Maintenance of landscaping works at Goa Medical College.

 
Contractors
M/s. Limboo Softscape,
Consultants
Inhouse (GSIDC)
 

See Similar Projects

Sewage & Effluent Treatment Plant

View Project

Repairs/Upgradation & Maintenance Of Government Schools In The State Of Goa – Civil, Plumbing & Electrical Works – Package-I (Pernem Taluka) – Rate Contract

View Project

Dismantling of HT overhead lines and supplying & laying of HT Underground cables at Porvorim

View Project