Project Duration
Stipulated Date of Commencement
September 04 2011
Stipulated Date of Completion /
Likely Date of Completion January 03 2012
Likely Date of Completion January 03 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 19,288,538.00
Awarded for
₹ 16,775,440.00
Project highlights
Medical Gas & Steel OT work.
Contractors
M/s. MDD Medical Systems (I) Pvt. Ltd.
Consultants
M/s Effective Architectural Services