Project Duration
Stipulated Date of Commencement February 19 2010
Stipulated Date of Completion /
Likely Date of Completion
August 18 2010
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,316,000.00
Awarded for ₹ 3,432,000.00

Project highlights

Lift work.

 
Gallery Image
Contractors
M/s. Thyssenkrupp Elevators (I) Pvt. Ltd.
Gallery Image
Consultants
M/s Effective Architectural Services
 
Similar Projects

See Similar Projects

Similar Project

Substation & external electrical works.

View Project
Similar Project

Supply, Installation, Testing and Commissioning of negative pressure VRDL lab at Goa Medical College and Hospital, Bambolim.

View Project
Similar Project

Construction of Forensic Block and Morgue for Goa Medical College at Bambolim

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.