Status
100%
Completed
Contractors
Consultants
Sub Works
This project involved 1 sub works. The details of the same available below
1
Civil works.
100% completed
Project Duration
Stipulated Date of Commencement
March 01 2014
Stipulated Date of Completion /
Likely Date of Completion July 30 2014
Likely Date of Completion July 30 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,857,508.00
Awarded for
₹ 4,404,197.00
Final Cost of Project
₹ 4,082,811.00
Project highlights
Construction of water storage tank for fire safety purpose
Contractors
M/s. K. V. Gaonkar,
Consultants
M/s. Frishmann Prabhu (I) Pvt. Ltd.