Project Duration
Stipulated Date of Commencement December 22 2013
Stipulated Date of Completion /
Likely Date of Completion
February 20 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 6,739,427.00
Awarded for ₹ 8,381,689.88
 
Gallery Image
Contractors
M/s. OVERSEAS ASSOCIATES
Gallery Image
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Interior works – Phase I.

View Project
Similar Project

Extension of R.M.O Hostel at Goa Medical College and Hospital, Bambolim, Goa S.H.: Supply, Installation, Testing and Commissioning of 11KV 4 Way outdoor type RMU and other allied works

View Project
Similar Project

Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in North Goa – S.H. – Repair of Chilled Water Type Cassette Units installed in OPDs and an AHU installed for an Operation Theatre at Sub District Hospital, Ponda Goa.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.