Project Duration
Stipulated Date of Commencement
October 21 2011
Stipulated Date of Completion /
Likely Date of Completion December 20 2011
Likely Date of Completion December 20 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,231,241.00
Awarded for
₹ 1,446,000.00
Contractors
M/s. Megastar Engineering
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.
See Similar Projects
Furniture works
View Project
Interior works
View Project
Networking, EPABX, UPS, Nurse Calling System, OPD System & Additional Electrical work.
View Project





