Project Duration
Stipulated Date of Commencement
February 06 2014
Stipulated Date of Completion /
Likely Date of Completion April 06 2014
Likely Date of Completion April 06 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 27,950,000.00
Awarded for
₹ 19,577,654.00
Contractors
M/S. PHILIPS ELECTRONICS INDIA LTD
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.
See Similar Projects
Upgradation of Ward Nos. 120, 123, 124, staff rest rooms and other miscellaneous works at Goa Medical College and Hospital at Bambolim, Goa : SH – Procurement of additional works/items and medical equipments required for Ward No.125 and Cardiovascular Surgical Operation Theatre – Supply, Installation and Testing and Commissioning of Dialysis Machine
View Project
Supply, installation, testing and commissioning of 20 passenger cum bed lift for plastic surgery ward at GMC & Hospital, Bambolim, Goa.
View Project
Supply, Installation,Testing and Commissioning of Incinerator for Goa Medical College & Hospital,Bambolim,Goa.
View Project