Project Duration
Stipulated Date of Commencement
July 18 2019
Stipulated Date of Completion /
Likely Date of Completion January 27 2020
Likely Date of Completion January 27 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 15,819,001.00
Awarded for
₹ 15,274,227.00
Project highlights
Supply, Installation,Testing and Commissioning of Incinerator for Goa Medical College

Contractors
M/s. Unitherm Engineering Services

Consultants
In-house (GSIDC)