Project Duration
Stipulated Date of Commencement
June 07 2018
Actual Date of Completion
August 28 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 20,000,000.00
Awarded for
₹ 17,500,000.00
Final Cost of Project
₹ 9,054,659.00