Project Duration
Stipulated Date of Commencement June 07 2018
Actual Date of Completion August 28 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 20,000,000.00
Awarded for ₹ 17,500,000.00
Final Cost of Project ₹ 9,054,659.00

Project highlights

furniture supply

 
Contractors
Infinity Modulus pvt ltd
Consultants
Inhouse
 