Project Duration
Stipulated Date of Commencement
January 29 2016
Stipulated Date of Completion /
Likely Date of Completion March 29 2016
Likely Date of Completion March 29 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,420,872.31
Awarded for
₹ 4,171,191.00
Project highlights
The scope of works includes electrical work

Contractors
M/s. Goa Friends Engineering & Electricals Pvt. Ltd.

Consultants
M/s. Rahul Deshpande Associates