Project Duration
Stipulated Date of Commencement
May 02 2016
Stipulated Date of Completion /
Likely Date of Completion April 03 2016
Likely Date of Completion April 03 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,516,970.00
Awarded for
₹ 3,212,332.00
Contractors
M/s.Installation Services
Consultants
M/s. Effective Architectural Services