Project Duration
Stipulated Date of Commencement May 02 2016
Stipulated Date of Completion /
Likely Date of Completion
April 03 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,516,970.00
Awarded for ₹ 3,212,332.00
 
Gallery Image
Contractors
M/s.Installation Services
Gallery Image
Consultants
M/s. Effective Architectural Services
 