Project Duration
Stipulated Date of Commencement
June 12 2012
Stipulated Date of Completion /
Likely Date of Completion May 02 2013
Likely Date of Completion May 02 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,839,786.00
Awarded for
₹ 6,220,033.00
Project highlights
Providing of structural work like catwalk, in the building
Contractors
M/s. T. S. Mistry
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
See Similar Projects
Development of Open space near Palmar Apartment
View Project
Area Lighting for Exposition 2014 at Old Goa
View Project
Phase II : Civil & Electrical work.
View Project





