Project Duration
Stipulated Date of Commencement
June 24 2006
Stipulated Date of Completion /
Likely Date of Completion April 23 2007
Likely Date of Completion April 23 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 111,151,947.00
Awarded for
₹ 141,357,588.70
Project highlights
The length of the road is 26.5 km. The work involves hot mixing of the road, construction of site gutters, retaining walls including pipe culverts cross drainages, road signages & marking, crash barriers.
Contractors
M/s. D. S. Contractors Private Limited
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD