Project Duration
Stipulated Date of Commencement
November 21 2014
Actual Date of Completion
May 20 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,468,500,000.00
Awarded for
₹ 1,459,500,000.00
Project highlights
The MSW treatment facility is a state-of-art, modern facility based on mechanical biological treatment process with proper segregation and bio-methanation technology. The facility has minimum human intervention, enclosed sheds, and computer-controlled / PLC/ SCADA equipment for handling different types of input material. Electricity produced in-house from the organic fraction of the waste is used to power the plant operation.
Contractors
M/s Hindustan Waste Treatment Pvt. Ltd., M/s Hindustan Waste Treatment Pvt. Ltd.
Consultants
Expert Committee consisting experts from NEERI, BARC, IIT Mubai, BITS Goa, Expert Committee consisting experts from NEERI, BARC, IIT Mubai, BITS Goa
See Similar Projects
Arena Work
View ProjectConstruction of Building for Food & Drugs Administration Block at Bambolim, Goa
View ProjectInternal, external and special lighting fixtures (Part B : External lights and façade lighting)
View Project