Project Duration
Stipulated Date of Commencement
December 15 2006
Stipulated Date of Completion /
Likely Date of Completion September 14 2007
Likely Date of Completion September 14 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 36,821,547.83
Awarded for
₹ 44,928,213.47
Project highlights
Hard landscaping includes upgradation of existing road networks, adequate pedestrian walkways, construction of planters, and basic infrastructural items like storm water drainage, irrigation system, erection of gates and other civil works related to landscape design.
Contractors
M/s. My Associates
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd