Project Duration
Stipulated Date of Commencement December 15 2006
Stipulated Date of Completion /
Likely Date of Completion
September 14 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 36,821,547.83
Awarded for ₹ 44,928,213.47

Project highlights

Hard landscaping includes upgradation of existing road networks, adequate pedestrian walkways, construction of planters, and basic infrastructural items like storm water drainage, irrigation system, erection of gates and other civil works related to landscape design.

 
Gallery Image
Contractors
M/s. My Associates
Gallery Image
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD
 
Similar Projects

See Similar Projects

Similar Project

Construction of Day Care Centre at Instuitute Psychiatry and Human Behaviour Complex (IPHB), Bambolim Goa

View Project
Similar Project

Upgradation of Ward Nos.120, 123, 124, Staff Rest Rooms (Old Garage) and other miscellaneous works at Goa Medical College and Hospital at Bambolim, Goa – Civil and plumbing works.

View Project
Similar Project

Surgery Instruments for C.T. (ICU) and Coronary Care Unit

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.