Project Duration
Stipulated Date of Commencement April 13 2016
Stipulated Date of Completion /
Likely Date of Completion
February 05 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,125,160.00
Awarded for ₹ 3,377,777.00

Project highlights

Civil, plumbing and dismantling work for office of STPI, Goa.

 
Gallery Image
Contractors
M/s. Harshada Trading co.
Gallery Image
Consultants
M/s. Pankaj Joshi Consultants
 
Similar Projects

See Similar Projects

Similar Project

Rejuvenation of cluster of lanes of Altinho Steps Phase II

View Project
Similar Project

Arranging Scaffolding

View Project
Similar Project

Upgradation of infrastructure in the rural areas under Deendayal Panchayat Raj Infrastructure Development (Golden Jubilee) Scheme 2013 – Reconstruction of Panchayat building at V.P.Honda.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.