Project Duration
Stipulated Date of Commencement
November 01 2005
Actual Date of Completion
November 11 2005
Status
100%
Completed
Cost (₹)
Estimated at
₹ 192,660.00
Awarded for
₹ 202,134.00
Final Cost of Project
₹ 181,237.00
Project highlights
Construction of sea wall.
Contractors
M/s. D. K. Bhomkar, M/s. D. K. Bhomkar
Consultants
M/s. TPF Engineering Pvt. Ltd