Project Duration
Stipulated Date of Commencement
January 22 2003
Stipulated Date of Completion /
Likely Date of Completion July 21 2003
Likely Date of Completion July 21 2003
Status
100%
Completed
Cost (₹)
Estimated at
₹ 68,776,953.00
Awarded for
₹ 76,639,000.00
Project highlights
The bridge has four spans out of which two spans are over the river basin supported on three numbers of piers located in the river. Both abutments are on the river bank, one on Sanvordem and other on Curchorem side. The width of the carriageway is 7.5 m + 1.5 m wide footpath on both sides of the carriageway.
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. TPF Engineering Pvt. Ltd.
See Similar Projects
Phase I : Land Development.
View Project
Construction of Bridge across Baga creek at Baga including approaches.
View Project
Maintenance of bridges constructed by GSIDC for a period of five years (North Goa) -Electrical work
View Project





