Project Duration
Stipulated Date of Commencement January 22 2003
Stipulated Date of Completion /
Likely Date of Completion
July 21 2003
Status
100%
Completed
Cost (₹)
Estimated at ₹ 68,776,953.00
Awarded for ₹ 76,639,000.00

Project highlights

The bridge has four spans out of which two spans are over the river basin supported on three numbers of piers located in the river. Both abutments are on the river bank, one on Sanvordem and other on Curchorem side. The width of the carriageway is 7.5 m + 1.5 m wide footpath on both sides of the carriageway.

 
Gallery Image
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Gallery Image
Consultants
M/s. TPF Engineering Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Construction of Bus Stand at Shiroda – Phase I : Land Development

View Project
Similar Project

Construction of bridge across river between Aldona and Calvim.

View Project
Similar Project

Design and Construction of bridge at Patto in Panaji including approach roads

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.