Project Duration
Stipulated Date of Commencement
January 22 2003
Stipulated Date of Completion /
Likely Date of Completion July 21 2003
Likely Date of Completion July 21 2003
Status
100%
Completed
Cost (₹)
Estimated at
₹ 68,776,953.00
Awarded for
₹ 76,639,000.00
Project highlights
The bridge has four spans out of which two spans are over the river basin supported on three numbers of piers located in the river. Both abutments are on the river bank, one on Sanvordem and other on Curchorem side. The width of the carriageway is 7.5 m + 1.5 m wide footpath on both sides of the carriageway.
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. TPF Engineering Pvt. Ltd.
See Similar Projects
Construction of Bus Stand at Marcel, Goa – Civil, Plumbing, Acoustic, Electrical, HVAC and Fire Fighting work.
View Project
Upgradation and improvement of roads leading to beaches in Pernem Phase–I Chopdem to Mandrem.
View Project
Hot mixing & Improvement of Road from Betul Bridge to Baradi Junction in Velim Constituency.
View Project





