Project Duration
Stipulated Date of Commencement April 28 2007
Stipulated Date of Completion /
Likely Date of Completion
October 27 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 26,781,679.10
Awarded for ₹ 37,000,000.05

Project highlights

The Restoration & refurbishment of FDA building and Maquinez palace was planned to house offices for Directorate of Film Festivals, Press Information Bureau, Media Centre, Offices of the Entertainment Society of Goa, Viewing rooms, Auditorium and associated infrastructure, Presentation room, Art Gallery, Film Museum, Print Unit and Storage, Guest Rooms, Associated functions of registration, conferences, briefing room, lounge, support facilities in toilets, services, etc.

 
Gallery Image
Contractors
M/s. D. S. Contractors Private Limited
Gallery Image
Consultants
M/s. Effective Architectural Services
 

Sub Works

This project involved 9 sub works. The details of the same available below

1

Interiors and Furniture work.

100% completed
 
Project Duration
Stipulated Date of Commencement October 08 2007
Stipulated Date of Completion /
Likely Date of Completion
November 07 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 17,758,464.82
Awarded for ₹ 16,967,500.48
 
Contractors
Contractors
M/s. Concept Creators
Consultants
Consultants
M/s. Effective Architectural Services
2

EPABX system.

100% completed
 
Project Duration
Stipulated Date of Commencement October 29 2007
Stipulated Date of Completion /
Likely Date of Completion
November 12 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 903,000.00
Awarded for ₹ 584,000.00
 
Contractors
Contractors
M/s. Coral Telecom Ltd.
Consultants
Consultants
M/s. Effective Architectural Services
3

Facilitation Services, Installation, Testing & Commissioning of Theatre equipments.

100% completed
 
Project Duration
Stipulated Date of Commencement September 28 2007
Stipulated Date of Completion /
Likely Date of Completion
November 07 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 730,340.00
Awarded for ₹ 730,340.00
 
Contractors
Contractors
M/s. MRH Digital Systems Pvt. Ltd.
Consultants
Consultants
M/s. Effective Architectural Services
4

Electrical works.

100% completed
 
Project Duration
Stipulated Date of Commencement October 04 2007
Stipulated Date of Completion /
Likely Date of Completion
October 31 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 23,930,239.00
Awarded for ₹ 28,515,999.00
 
Contractors
Contractors
M/s. Goa Friends Engineering & Electricals Pvt. Ltd.
Consultants
Consultants
M/s. Effective Architectural Services
5

Theatre System (non-proprietory).

100% completed
 
Project Duration
Stipulated Date of Commencement October 04 2007
Stipulated Date of Completion /
Likely Date of Completion
November 03 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 10,243,325.00
Awarded for ₹ 11,842,038.03
 
Contractors
Contractors
M/s. MRH Digital Systems Pvt. Ltd.
Consultants
Consultants
M/s. Effective Architectural Services
6

Construction of RCC sump and pumping system.

100% completed
 
Project Duration
Stipulated Date of Commencement October 16 2008
Stipulated Date of Completion /
Likely Date of Completion
November 29 2008
Status
100%
Completed
Cost (₹)
Estimated at ₹ 8,50,542.00
Awarded for ₹ 1,095,710.50
 
Contractors
Contractors
M/s.P. Gangadharan
Consultants
Consultants
M/s. Effective Architectural Services
7

HVAC works.

100% completed
 
Project Duration
Stipulated Date of Commencement October 08 2007
Stipulated Date of Completion /
Likely Date of Completion
November 07 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 17,395,782.00
Awarded for ₹ 19,798,057.87
 
Contractors
Contractors
M/s. ETA General Pvt. Ltd.
Consultants
Consultants
M/s. Effective Architectural Services
8

Fire Hydrant / Alarm System.

100% completed
 
Project Duration
Stipulated Date of Commencement October 29 2007
Stipulated Date of Completion /
Likely Date of Completion
November 12 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,517,253.00
Awarded for ₹ 3,910,525.00
 
Contractors
Contractors
M/s. Max Alert Systems Pvt. Ltd
Consultants
Consultants
M/s. Effective Architectural Services
9

Additional miscellaneous works

100% completed
 
Project Duration
Stipulated Date of Commencement June 09 2009
Stipulated Date of Completion /
Likely Date of Completion
September 07 2009
Status
100%
Completed
Cost (₹)
Estimated at ₹ 4,343,352.00
Awarded for ₹ 4,609,470.95
 
Contractors
Contractors
M/s. Deshpande Constructions
Consultants
Consultants
M/s. Effective Architectural Services
Similar Projects

See Similar Projects

Similar Project

Construction of two number of sheds for treatment of dry waste within the Corporation of the City of Panaji (CCP) jurisdiction.

View Project
Similar Project

Interior & Furniture work

View Project
Similar Project

Supply & Installation of Compactors in Record Room of Survey Department and Sub Civil Registrar.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.