Status
100%
Completed
Project highlights
Collecting and segregating solid waste material strewn on eiher sides of National Highway NH-17, NH-17A and NH-17B within Goa, transportation and storing at designated locations
Contractors
Consultants
Sub Works
This project involved 6 sub works. The details of the same available below
1
Panaji to Patradevi (Part I) – Chainage 0.00 km. to 21.90 km.
100% completed
Project Duration
Stipulated Date of Commencement
March 21 2013
Stipulated Date of Completion /
Likely Date of Completion January 10 2015
Likely Date of Completion January 10 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 853,639.00
Awarded for
₹ 840,171.60
Final Cost of Project
₹ 6,036,450.00
Contractors
Consultants
2
Panaji to Patradevi (Part II) – Chainage 21.90 km. to 43.80 km.
100% completed
Project Duration
Stipulated Date of Commencement
March 21 2013
Stipulated Date of Completion /
Likely Date of Completion January 10 2015
Likely Date of Completion January 10 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 853,639.00
Awarded for
₹ 840,171.60
Final Cost of Project
₹ 6,036,450.00
Contractors
Consultants
3
Panaji to Pollem (Part I) – Chainage 0.00 km. to 31.30 km.
100% completed
Project Duration
Stipulated Date of Commencement
April 01 2013
Stipulated Date of Completion /
Likely Date of Completion January 10 2015
Likely Date of Completion January 10 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,219,904.00
Awarded for
₹ 1,280,289.25
Final Cost of Project
₹ 8,008,826.00
Contractors
Consultants
4
Panaji to Pollem (Part II) – Chainage 31.30 km. to 62.60 km.
100% completed
Project Duration
Stipulated Date of Commencement
April 01 2013
Stipulated Date of Completion /
Likely Date of Completion January 10 2015
Likely Date of Completion January 10 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,219,904.00
Awarded for
₹ 1,157,599.20
Final Cost of Project
₹ 8,405,177.00
Contractors
Consultants
5
Panaji to Pollem (Part III) – Chainage 62.60 km. to 93.90 km.
100% completed
Project Duration
Stipulated Date of Commencement
April 16 2013
Stipulated Date of Completion /
Likely Date of Completion January 10 2015
Likely Date of Completion January 10 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,219,904.00
Awarded for
₹ 1,123,044.00
Final Cost of Project
₹ 8,129,862.00
Contractors
Consultants
6
Cortalim to Verna via Airport – 24.00 km.
100% completed
Project Duration
Stipulated Date of Commencement
April 16 2013
Stipulated Date of Completion /
Likely Date of Completion January 10 2015
Likely Date of Completion January 10 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 935,546.00
Awarded for
₹ 880,992.00
Final Cost of Project
₹ 6,396,768.00
Contractors
Consultants
See Similar Projects
Repairs and painting of DB Marg and other roads for IFFI 2014.
View ProjectLandscape and external development works at Multiplex Courtyard.
View ProjectPackage III (VP Azossim-Mandur-Dongrim & VP Neura).
View Project