Status
100%
Completed

Project highlights

Collecting and segregating solid waste material strewn on eiher sides of National Highway NH-17, NH-17A and NH-17B within Goa, transportation and storing at designated locations

 
Contractors
Consultants
 

Sub Works

This project involved 6 sub works. The details of the same available below

1

Panaji to Patradevi (Part I) – Chainage 0.00 km. to 21.90 km.

100% completed
 
Project Duration
Stipulated Date of Commencement March 21 2013
Stipulated Date of Completion /
Likely Date of Completion
January 10 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 853,639.00
Awarded for ₹ 840,171.60
Final Cost of Project ₹ 6,036,450.00
 
Contractors
Consultants
2

Panaji to Patradevi (Part II) – Chainage 21.90 km. to 43.80 km.

100% completed
 
Project Duration
Stipulated Date of Commencement March 21 2013
Stipulated Date of Completion /
Likely Date of Completion
January 10 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 853,639.00
Awarded for ₹ 840,171.60
Final Cost of Project ₹ 6,036,450.00
 
Contractors
Consultants
3

Panaji to Pollem (Part I) – Chainage 0.00 km. to 31.30 km.

100% completed
 
Project Duration
Stipulated Date of Commencement April 01 2013
Stipulated Date of Completion /
Likely Date of Completion
January 10 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,219,904.00
Awarded for ₹ 1,280,289.25
Final Cost of Project ₹ 8,008,826.00
 
Contractors
Consultants
4

Panaji to Pollem (Part II) – Chainage 31.30 km. to 62.60 km.

100% completed
 
Project Duration
Stipulated Date of Commencement April 01 2013
Stipulated Date of Completion /
Likely Date of Completion
January 10 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,219,904.00
Awarded for ₹ 1,157,599.20
Final Cost of Project ₹ 8,405,177.00
 
Contractors
Consultants
5

Panaji to Pollem (Part III) – Chainage 62.60 km. to 93.90 km.

100% completed
 
Project Duration
Stipulated Date of Commencement April 16 2013
Stipulated Date of Completion /
Likely Date of Completion
January 10 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,219,904.00
Awarded for ₹ 1,123,044.00
Final Cost of Project ₹ 8,129,862.00
 
Contractors
Consultants
6

Cortalim to Verna via Airport – 24.00 km.

100% completed
 
Project Duration
Stipulated Date of Commencement April 16 2013
Stipulated Date of Completion /
Likely Date of Completion
January 10 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 935,546.00
Awarded for ₹ 880,992.00
Final Cost of Project ₹ 6,396,768.00
 
Contractors
Consultants

See Similar Projects

Repairs and painting of DB Marg and other roads for IFFI 2014.

View Project

Landscape and external development works at Multiplex Courtyard.

View Project

Package III (VP Azossim-Mandur-Dongrim & VP Neura).

View Project
x