Project Duration
Stipulated Date of Commencement July 14 2004
Stipulated Date of Completion /
Likely Date of Completion
October 31 2004
Status
100%
Completed
Cost (₹)
Estimated at ₹ 227,419,000.00
Awarded for ₹ 241,764,000.00

Project highlights

Repairs and restoration works, air conditioning, furniture / interior work, road work and plumbing plus electrical work.

 
Gallery Image
Contractors
M/s. Unity Infraprojects Ltd.
Gallery Image
Consultants
M/s. UCJ Architecture & Environment
 
Similar Projects

See Similar Projects

Similar Project

Construction of Panchayat Building at Mauxi in Sattari Taluka.

View Project
Similar Project

Extension of temporary jetty near Kala Academy.

View Project
Similar Project

CCTV works

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.