Project Duration
Stipulated Date of Commencement November 05 2018
Stipulated Date of Completion /
Likely Date of Completion
February 04 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,280,454.50
Awarded for ₹ 2,238,626.00

Project highlights

Replacement of failed cables and supply, installation of new fixtures, spares for the streetlights

 
Gallery Image
Contractors
M/s. James Electrical
Gallery Image
Consultants
In-house (GSIDC)
 
Similar Projects

See Similar Projects

Similar Project

Renovation of office premisies of Regional Employment Exchange, Panaji

View Project
Similar Project

Construction of building at Patto with provision for Gas insulated substation Panaji Phase I

View Project
Similar Project

Strengthening of FDA laboratories, Bambolim Goa

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.