Project Duration
Stipulated Date of Commencement
August 31 2017
Stipulated Date of Completion /
Likely Date of Completion April 30 2018
Likely Date of Completion April 30 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 29,480,548.00
Awarded for
₹ 32,564,020.00
Project highlights
Repair/Upgrdation works of schools which includes roofing ,tiling,dadoes,painting etc.
Contractors
M/s.Devang Constrction
Consultants
M/s.Creative Abode