Project Duration
Stipulated Date of Commencement
January 30 2019
Stipulated Date of Completion /
Likely Date of Completion December 08 2019
Likely Date of Completion December 08 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,426,491.00
Awarded for
₹ 7,911,250.50
Project highlights
Repairs of Govt. Schools in Pernem Taluka – Civil, Plumbing, Electrical works
Contractors
M/s. Sunil Enterprises
Consultants
M/s. Oracle Structural Consultants