Project Duration
Stipulated Date of Commencement
February 05 2021
Stipulated Date of Completion /
Likely Date of Completion October 19 2021
Likely Date of Completion October 19 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 12,244,766.00
Awarded for
₹ 12,591,887.23
Project highlights
Repairs/Upgradation & Maintenance of Govt. schools in the state of Goa
Contractors
M/s. Manup Infrastructures,
Consultants
M/s. Vaishali Pednekar Associates