Project Duration
Stipulated Date of Commencement
June 28 2018
Stipulated Date of Completion /
Likely Date of Completion March 11 2019
Likely Date of Completion March 11 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 10,049,600.00
Awarded for
₹ 10,973,975.15
Project highlights
Repairs/Upgradation & maintenance of Government Schools
Contractors
M/s. K. G. Thomas
Consultants
M/s. Creative Abode
See Similar Projects
Improvement and Construction of Football Ground and Panchayat Ghar at Village Panchayat Batim in St. Andre Constituency.
View Project
Repairs/Upgradation and Maintenance of Govt. Schools in the state of Goa – Civil, Plumbing and Electrical works -Bicholim Taluka- Package B-(G.P.S. Amona, G.P.S. Digne Surla, G.P.S. Kharwada Amona, G.P.S. Maini Navelim, G.P.S. Nawarwada Pale, G.P.S. Rumad Surla, G.P.S.Khodgini Surla, G.P.S. Khajan Surla )