Project Duration
Stipulated Date of Commencement
April 27 2018
Stipulated Date of Completion /
Likely Date of Completion June 11 2019
Likely Date of Completion June 11 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,122,859.00
Awarded for
₹ 6,663,845.07
Project highlights
Repairs/ Upgradation & Maintenance of schools
Contractors
M/s.Nilambari Constructions
Consultants
M/s.Allwyn Crasto