Project Duration
Stipulated Date of Commencement
September 18 2019
Stipulated Date of Completion /
Likely Date of Completion March 03 2019
Likely Date of Completion March 03 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,755,042.00
Awarded for
₹ 7,558,715.77
Project highlights
Repairs of Govt. Schools in Pernem Taluka – Civil, Plumbing, Electrical works
Contractors
M/s. Race Constructions
Consultants
M/s. Vaishali Pednekar Associates
See Similar Projects
Construction of Concrete Road for Ashram school under centrally sponsored scheme of Ministry of Tribal Affairs at “MOSHIPHOND” in the Land under Survey no. 20/0 in the Village Poinguinim of Canacona Taluka.
View Project
Repairs/upgradation & maintenance of Government primary Schools in the state of Goa -Civil, plumbing and electrical works-package A – GPS Ghadiwada GPS Deulmol Sirvoi, GPS Deulamol Markarnem and GPS Pontemol.
View Project
Repairs/ Upgradation & Maintenance of Government Schools in the State of Goa – Civil, Plumbing & Electrical – GHS Zambaulim
View Project