Project Duration
Stipulated Date of Commencement
September 20 2017
Stipulated Date of Completion /
Likely Date of Completion September 19 2018
Likely Date of Completion September 19 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 50,00,000.00
Awarded for
₹ 59,42,392.51
Project highlights
Repair/Upgrdation works of schools which includes roofing ,tiling,dadoes,painting etc.
Contractors
M/s. S M Realtors
Consultants
M/s. Vaishali Pednekar Associates