Project Duration
Stipulated Date of Commencement January 22 2019
Actual Date of Completion November 10 2021
Status
100%
Completed
Cost (₹)
Estimated at ₹ 9,740,455.00
Awarded for ₹ 10,889,310.58
Final Cost of Project ₹ Rs.36,99,117.29

Project highlights

Repairs/Upgradation & Maintenance of Government Schools

 
Contractors
M/s. Sirajuddin beig
Consultants
M/s. Bhaskar Wagle & Associates
 