Project Duration
Stipulated Date of Commencement December 19 2018
Stipulated Date of Completion /
Likely Date of Completion
June 19 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,824,596.00
Awarded for ₹ 3,063,396.61

Project highlights

Repairs/Upgradation and maintenance of Government schools in the state of Goa – Sattari Taluka

 
Gallery Image
Contractors
M/s. Manup Infrastructures
Gallery Image
Consultants
M/s. Bhaskar Wagle and Associates
 
Similar Projects

See Similar Projects

Similar Project

Construction of Government College of Commerce & Economics at Borda, Margao, Goa – Civil, plumbing, electrical, lift and fire fighting – Phase I.

View Project
Similar Project

Infrastructure works for Sanjay Centre for Special Education at Porvorim

View Project
Similar Project

Construction of Anganwadi Centres from NABARD Assistance – Package III (GPS Pernem, GPS Mandrem, GPS Korgao).

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.