Project Duration
Stipulated Date of Commencement August 29 2017
Actual Date of Completion May 31 2020
Status
100%
Completed
Cost (₹)
Estimated at ₹ 5,000,000.00
Awarded for ₹ 5,000,000.00
Final Cost of Project ₹ 1,100,000.00

Project highlights

Repair/Upgrdation works of schools which includes roofing ,tiling,dadoes,painting etc.

 
Contractors
M/s Rahul Constructions
Consultants
M/s Manoj Amshekar (PMC)
 