Project Duration
Stipulated Date of Commencement
January 31 2019
Stipulated Date of Completion /
Likely Date of Completion October 09 2019
Likely Date of Completion October 09 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 10,244,600.42
Awarded for
₹ 12,013,000.00
Project highlights
Repairs/ Upgradation & Maintenance of schools
Contractors
M/s. Shrusti Construction
Consultants
M/s. Nitin Arolkar