Project Duration
Stipulated Date of Commencement
January 31 2019
Stipulated Date of Completion /
Likely Date of Completion October 09 2019
Likely Date of Completion October 09 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 10,244,600.42
Awarded for
₹ 12,013,000.00
Project highlights
Repairs/ Upgradation & Maintenance of schools
Contractors
M/s. Shrusti Construction
Consultants
M/s. Nitin Arolkar
See Similar Projects
Repairs/Upgradation and maintenance of Government Schools in the state of Goa- Civil Plumbing and Electrical works:-Bicholim Taluka – Package K ( G.P.S Vathadev – Sarvan , G.P.S. Paltadwada, G.P.S. Naigini – Kudchire and G.P.S Kholpewadi – Sal )
View Project
Repairs/Upgradation & Maintenance of Government Schools in the State of Goa – Civil, Plumbing & Electrical works in Bicholim Taluka – Package J (G.P.S Valshi, G.P.S. Ussap, G.P.S. Kharpal and G.P.S Dhangarwada)
View Project
Construction of Government Primary School at Dattagad, Bethora, Ponda Goa – Civil, Plumbing & Electrical works
View Project