Project Duration
Stipulated Date of Commencement January 03 2019
Stipulated Date of Completion /
Likely Date of Completion
September 12 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 9,794,104.29
Awarded for ₹ 11,189,253.28

Project highlights

Repairs/ Upgradation & Maintenance of schools

 
Gallery Image
Contractors
M/s. Sirajuddin Beig
Gallery Image
Consultants
M/s. Nitin Arolkar
 
Similar Projects

See Similar Projects

Similar Project

Repairs/ upgradation & maintenance of Government School in the State of Goa – GHS Daushire

View Project
Similar Project

Construction of building for Boys’ hostel at Goa University Campus – Civil & Plumbing works

View Project
Similar Project

Construction of Compound Wall for Ashram school under centrally sponsored scheme of Ministry of Tribal Affairs at “MOSHIPHOND” in the Land under Survey no. 20/0 in the Village Poinguinim of Canacona Taluka.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.