Project Duration
Stipulated Date of Commencement March 07 2019
Stipulated Date of Completion /
Likely Date of Completion
November 20 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 12,795,370.00
Awarded for ₹ 13,724,359.85

Project highlights

Repairs/Upgradation of School

 
Gallery Image
Contractors
M/s. K. G. Thomas
Gallery Image
Consultants
M/s. Creative Abode.
 
Similar Projects

See Similar Projects

Similar Project

Construction of Higher Secondary School building for Dr.K.B.Hedgewar Higher Secondary School at Cujira, Bambolim,Tiswadi,Goa.

View Project
Similar Project

Furniture work.

View Project
Similar Project

Construction of Government Primary School at Guddemol, Sanguem, Goa.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.