Project Duration
Stipulated Date of Commencement
January 25 2019
Actual Date of Completion
September 25 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 62,31,102.33.
Awarded for
₹ 5,177,777.00
Final Cost of Project
₹ 4611489
Project highlights
2,68,85,072.00.
Contractors
M/s. Harshada Trading Company
Consultants
M/s. Pankaj Joshi Consultants