Project Duration
Stipulated Date of Commencement April 18 2022
Stipulated Date of Completion /
Likely Date of Completion
August 30 2024
Status
30%
Completed
Cost (₹)
Estimated at ₹ 11,680,980.00
Awarded for ₹ 12,055,767.00

Project highlights

The scope of work includes construction of Concrete road, laying of pavers, etc.

 
Gallery Image
Contractors
M/s. A.R. Constructions
Gallery Image
Consultants
M/s Structwel Designers and Consultant Pvt. Ltd
 
Similar Projects

See Similar Projects

Similar Project

Construction of Panchayat Building in Keri in Sattari Taluka.

View Project
Similar Project

Reconstruction of Panchayat Ghar along with commercial shops, hall and other amenities for administrative purpose at Molcornem, Quepem, Goa.

View Project
Similar Project

Construction of Panchayat Building along with Multipurpose Hall for Village Panchayat Curdi in Sanguem Taluka.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.